Harford Nationwide Turnkey Installations |
|
|
Pre-installation activities include the following:
|
- Field Measurements: Upon request of the General Contractor or End User, field measurements are to be taken by the Installing Contractor as soon as the job site is accessible.
- Delivery: The Installing Contractor is to meet the shipment at the job site and unload; or, the shipment may be delivered to the Installer’s warehouse for subsequent delivery by the Installer to the job site, with no additional charges incurred. This is usually at the option of the Installing Contractor. If the usage of a fork lift is required for loading and/or unloading, it is to be supplied by the Installing Contractor at no additional charge.
|
|
Installation is to include the following:
|
- Panels: All wall, ceiling and floor panels.
- Doors: Doors are to be installed and adjusted for proper fit and operation. This includes all solid, glass, sliding (electric and manual), and/or reach-in doors. ANCHOR PLATES are to be installed BEFORE tiling of the general floor area.
- Structural Supports: Any structural steel supports and/or suspended ceiling systems for ceiling panels (wire and clip), if applicable.
- Roof Cap: Roof Cap for outside/outdoor installation, if applicable. [PENETRATIONS & CURBS are the responsibility of the G. C. / Roofer.]
- Trim: Closure panels, coved base, and trim strips, if applicable.
- Crane: If the usage of a crane is necessary, it is to be supplied by the Installer.
- Dunnage: Dunnage removal is the responsibility of the Installing Contractor. At a
new construction site, it is assumed that the G.C. will supply the dumpster for dunnage.
- Shelfs: With glass reach-in doors, the Installer is responsible for installing the top and bottom shelfs only.
|
|
Refrigeration System installation is to include the following:
|
- Line Runs: Condensing Unit(s) and Evaporator(s) within 50 feet.
- Piping: Hard Copper is supplied by Installer, unless otherwise specified.
- Line Insulation: Insulation is to be supplied by the Installer.
- Drain Lines: Running of Condensate Drain Line in Copper within 20’ of coil.
- Insulation: Insulated heat tape is to be supplied by the Installer, and used throughout the walk-in freezer section.
- Racks: If a compressor rack is required for an installation, a written quotation from the Installing Contractor is requested PRIOR to obtaining of such equipment. An additional Purchase Order from Refrigeration Alliance will be issued for this equipment.
- Start-Up: Start-up is included with installation and may require a return trip after the initial installation, due to the job site readiness and status of electrical hook-up.
- Completion/Component Check-Off: Completion Sheet and Installation/Component Operation Check List must be completed for each installation. The Sign-Off/Completion Sheet must be completed and returned before final payment can be scheduled.
|
|
Electrician Work is as follows:
|
- Final Connections: Final connections are performed by a qualified electrician [provided “By Others/G.C.”]. The Installing Contractor may supervise the electrician in making these connections. If a qualified electrician is NOT supplied “by others” and the Installing Contractor is asked to perform this service, a written quotation from the Installing Contractor to Refrigeration Alliance is necessary PRIOR to any work, for any amendment to the original purchase order. All invoicing for approved “extras” must be billed separately from the installation invoice.
|
|
Warranty coverage is as follows:
|
- 90-Days Labor Warranty: The Installer is to provide 90-days Labor/Service warranty. This is all-inclusive: labor, refrigerant, trip/travel charges, etc.
- Out-of-Warranty Calls: Out-of warranty service calls may be requested.
If applicable, the Installing Contractor should directly invoice the job location/end-user.
|
|
Additional items not listed on the Purchase Order:
|
- Extras: In the event that unforeseen circumstances arise which effect the installation, a written quotation from the Installing Contractor to Refrigeration Alliance is necessary for any amendment to the original purchase order. The request for additional work and/or equipment and the approval for such work and/or equipment must be received PRIOR to commencement. All invoicing for approved “extras” must be billed separately from the installation invoice.
- Sub-Contracting: All work must be performed by the employees to whom the Purchase Order was issued. Sub-contracting is not permitted without written authorization from Refrigeration Alliance.
- Taxes: The Purchase Order issued by Refrigeration Alliance is inclusive of any/all taxes for which the Installing Contractor may be responsible. Refrigeration Alliance is
not liable for any taxes. Applicable applied taxes will be billed to Customer.
|
|
Excluded items from the installation are as follows:
|
- Core Boring: Core boring is not included in a standard installation.
- Concrete: The pouring and/or leveling of concrete [curbs, pads, etc.].
is not included in a standard installation.
- Penetrations: No penetrations are to be performed by the Installing Contractor. The G.C. must have roof penetrations performed by his roofer.
- Permits: Local, State, County, City, Township and/or Mechanical Permits are not
included in the standard installation policy. If an Installing Contractor is asked to obtain a permit, the price of the permit, including travel time, is to be submitted on a separate invoice.
- Air Gap: Contractor should leave approximately 2” of air gap around the walk-in panels, for proper installation.
|
|
Notes to the Installing Contractor and End-User regarding the installation:
|
- Scheduling: 72-hour advance notice is required for the scheduling of an installation. The Installing Contractor will be provided with the name and phone number of the freight company, along with the shipment “Pro Number,” so that the delivery may be traced to its’ final destination location. It is the responsibility of the Installer to contact the freight carrier to arrange for the delivery time and date of the shipment. Neither RA nor the Shipper are responsible for charges that may occur as a result of lost time awaiting freight deliveries that have been scheduled between the installer and the freight company. If you are notified from RA that a shipment is arriving via a “Dedicated Carrier” the installer is expected to be at the job site to accept delivery at the appointed time (usually 8 a.m.) unless otherwise notified.
- Lost Time: If the Installing Contractor is asked to report to the job site on a specific day and time and, upon arrival, the job is not ready for installation, additional charges may be incurred. Refrigeration Alliance must be notified immediately if an installation and/or delivery can not take place as scheduled. If imposed, maximum additional charges will not exceed one full-day’s wages for two (2) men including travel time. Minimum additional charges will not exceed two hours wages for (2) men each, including travel time.
- Additions, Deletions, Exclusions: : Any additions, deletions and/or exclusions to the standard installation policy must be noted in writing and clearly marked on the job quotation, specifications and Purchase Orders issued.
- Legal Fees Incurred: Should a dispute arise regarding any area of the performance of the installation contract which requires or results in subsequent litigation, all legal fees incurred will be the sole responsibility of the “losing” party against which the resultant judgment is found.
- Jurisdiction: This Agreement and subsequent contract is negotiated and empowered in the State of California and the County of San Diego, and as such is subject to all relevant laws and regulations.
- Dress: All installers are to be dressed appropriately for safety considerations, with hard hat, work shoes, and eye/ear protection if necessary. All precautions must be taken when working with hazardous chemicals or machinery. Easily identifiable work shirts (with sleeves) and long pants should be worn by the installing crew.
- Union Labor/Prevailing Wages: All standard installation prices/quotations from Refrigeration Alliance are based upon Non-Union Labor and Non-Prevailing Wage Rates, and all work is to occur during a standard 40-hour workweek. The End-User should submit a written request for a Union Installation, and a supplemental quotation will be provided by Refrigeration Alliance. Any interference from Labor Union Agents or Officials during an installation may result in an increase in the original contracted price from Refrigeration Alliance, and additional costs incurred as a result of union involvement will be added to the original contracted price. Refrigeration Alliance will notify the end-user if any charges are likely to be incurred.
|
| |
| Back to Installation Services
|
|
| |